To build a new operating unit within an existing and operating petrochemical facility. STI was tasked with the installation of piping, steel, elevated foundations, setting of the equipment and the
Project Description: Earthworks, Civil Foundations, Structural Steel Erection, Piping Installation, Equipment Setting and I&E. Key Stats: • 62,000 Linear Feet of Piping • 1,400 Tons of Steel • 25 Acres
This field construction projects consisted of installing over 25,000 CY of Concrete, 2,500 tons of rebar, 41,000 CY of select fill, 90,000 LF of piping, Erecting 3,500/Tons of Steel and
STI Group was selected as the contractor to erect a Waste Heat Boiler and all associated equipment at Rain CII in Sulphur, LA. The project included the erection of the
Overview The Motiva Refinery, located in Port Arthur, Texas, has a daily crude oil processing capacity of 600,000 barrels per day. The Port Arthur Crude Expansion Project was a $7
Our fabrication projects consist of large capital projects with thousands of spools to one spool orders. On this project STI fabricated and delivered over 5,300 spools. Size ranged from 1/2"
Overview The mast is one of the most integral pieces in a drilling operation. This steel structure keeps the drilling rig connected with the drilling machinery while allowing easier access
Overview Both the production and the demand for crude oil is at an all-time high in the United States and it is expected to continuing growing exponentially. Strategically, the Southeast