Confidential Expansion

Client

Confidential

Location

Colorado, USA

Industry

Steel

Year

2023-05-01T05:00:00-04:00

This field construction projects consisted of installing over 25,000 CY of Concrete, 2,500 tons of rebar, 41,000 CY of select fill, 90,000 LF of piping, Erecting 3,500/Tons of Steel and Setting 185 pieces of equipment. STI’s role consisted of civil, mechanical, piping, structural and millwright work.

Project Description

Earthworks, Civil Foundations, Structural Steel Erection, Piping Installation, Equipment Setting and the Erection of a Walking Beam Furnace.

This Projects Summary of Stats

Concrete – 25,000 CY • Select Fill – 41,000 CY • Flow Fill – 25,000 CY • Rebar – 2,500 TN • Piping –90,000 LF • Structural Steel –3,500 TN • Equipment Set –185 Pieces • Erection of Walking Beam Furnace • Peak Headcount –465